Who gets to build first? Why suppliers hold the key to infrastructure growth
Words by Adnan Ghotmi, Pedro Barroso
Infrastructure developers face a trade-off: commit capital before customers and permits are secured, or risk losing the equipment and contractors needed to deliver. A strategic approach to commitments can secure capacity while preserving flexibility as plans evolve.
Infrastructure development has always required capital commitments ahead of revenue certainty. In some markets, however, longer lead times and constrained supplier capacity are pushing material commitments earlier in the development cycle. Delivering an energy or data centre project on schedule can require orders for hundreds of millions of dollars of equipment before the customer has signed and before permits are in place. Meanwhile, major customers, including hyperscalers, continue to reassess when and where they need capacity. Speed to market can be decisive in winning that business, alongside power availability, location, cost and confidence in delivery.
Suppliers have their own risk to manage. Reserving manufacturing slots, engineering resources or specialist labour for a project that might not proceed can mean turning away other work.
For some developers, access to equipment, contractors and supplier capacity can become as significant a constraint on growth as access to funding. Has the business actually secured the resources it needs? Will suppliers prioritise it when the market tightens? And how much commercial risk is it prepared to carry to secure that capacity? However, committing before demand is certain can leave capital tied up in projects that are delayed, redesigned or cancelled.
Leaders therefore need to consider how mature each project is and how likely it is to proceed before making a commitment. They must decide where committing early is worth the exposure, how that risk should be allocated and where the business needs to retain flexibility.
Large companies are not always large customers
In constrained markets, supplier selectivity can become a significant limit on growth. Businesses entering a new region can find that local contractors with the relevant capability are committed to existing clients, while a single project may offer too little work to attract bidders from further afield.
Procuring project by project keeps supplier relationships transactional, giving suppliers little reason to reserve capacity for work that may not recur. This may cause few problems while capacity is plentiful, but when conditions tighten, it can mean higher costs and delayed projects as suppliers reprice, offer later delivery slots or prioritise more attractive projects.
The problem becomes more acute when a business tries to scale. A company with an ambitious development pipeline may discover that the suppliers it needs are already committed to competitors with longer-standing relationships. Size offers little advantage if suppliers see only a succession of individual projects rather than credible, executable demand. A pipeline without clear funding, approvals, specifications or decision dates may carry less weight than a smaller but more certain programme.
Balance commitment and flexibility across the pipeline
Businesses can strengthen their position with suppliers by bringing together credible demand across their development pipeline, provided specifications and delivery requirements are sufficiently common to support portfolio-level arrangements. That can allow a developer to distinguish firm orders for mature projects from capacity reservations, staged commitments or conversion options for less certain demand. Advance payments, cancellation provisions and agreed allocation rights can make it more attractive for suppliers to reserve capacity.
The aim is to create options. This means securing access to critical resources while retaining the ability to adjust plans as customer demand, technology and market conditions change. That requires commercial arrangements that reflect both the value of assured access and the cost of flexibility, with commitment thresholds linked to project maturity and investment governance.
A major power and water infrastructure programme supporting AI and data-centre growth shows how selective early commitments can work. With fixed energisation deadlines and long lead times for transformers and switchgear, the developer ordered critical equipment directly from manufacturers before appointing EPC contractors. The contracts were later transferred to the selected EPCs, securing equipment while allowing the broader EPC packages to be competitively procured. Flexibility came from separating the timing of equipment orders from the broader procurement process.
Know what suppliers can really deliver
Making those commitments also depends on having reliable information about what suppliers can deliver. Published cost benchmarks and market reports may provide a starting point, but they cannot necessarily establish the prices, capacity or lead times available for a particular project in a particular market. That intelligence often comes through direct supplier engagement, local expertise and established commercial relationships.
Visibility beyond immediate suppliers matters too. Reserving capacity with a manufacturer does not guarantee that the equipment will arrive on time. Critical components, production schedules, testing capacity, specialist labour and logistics can all cause delays. Understanding those dependencies helps businesses judge whether the capacity they believe they've secured will be available when needed.
These issues also affect the assumptions behind major investments, the exposure taken before final approval and the confidence leaders can place in delivery plans.
Commitments only create value if the business can act on them
Simply securing capacity early does not insulate a business from disruption. One large energy and data centre developer reserved capacity covering the next two and a half years. It secured all its critical long-lead equipment on time, accelerated EPC contract awards and achieved savings of more than 9% against its target baseline. Yet when it came to delivery, it still faced price escalation, force majeure notices and a blocked waterway that forced it to use a longer shipping route.
Because the organisation had built governance around the programme and adopted a risk-based approach to managing its supply chain, it was better prepared to respond. A crisis committee and fast-track approval route allowed urgent decisions to be made without waiting for the usual approval process. Savings and scheduling gains secured through procurement helped absorb the unexpected delivery and logistics problems.
Before disruption occurs, leaders should consider how decisions will be made when costs increase, suppliers cannot deliver or project requirements shift. Who has the authority to change course, and at what escalation threshold? How quickly can competing commercial priorities be resolved? And does the organisation have the information and expertise to evaluate those trade-offs across the wider portfolio, rather than one project at a time?
In capacity-constrained markets, the ability to deliver growth may depend on decisions made long before a project is approved. Developers should assess supply commitments with the same care as other investment decisions. They need to commit early where access is critical delivery paths, preserving options where uncertainty remains, and retaining the capabilities to act when circumstances change.
How we can help
Efficio helps procurement and supply chain leaders build the capabilities to find, deliver and protect value in volatile markets. Combining deep commercial and operational expertise with data-driven insights and hands-on implementation, we help organisations navigate complex trade-offs, strengthen supply chain performance and turn disruption into opportunity.